Basis of design for FPSO decommissioning & tow

Floating Solutions Consulting (FSC) was engaged to develop a comprehensive Basis of Design (BoD) for the decommissioning and relocation of an FPSO. This foundational work established a single source of truth for all technical, regulatory, and operational planning.

The challenge

Relocating and decommissioning a large FPSO involved significant technical, regulatory, and commercial risks. The main challenges were:

  • Uncertainty over suitable recycling yard options, both in Australia and internationally, each with unique access, environmental, and operational constraints.
  • Gaps in technical data, regulatory requirements (AMSA, IMO, Flag State, Customs/Quarantine), and insurance/class coverage for the tow.
  • High financial and reputational risk if the wrong methodology or destination was selected.
  • The need for a comprehensive, multi-disciplinary approach to scenario planning, risk identification, and cost estimation.

Our solution

We assembled a multi-disciplinary team to develop a rigorous BoD, collating the available technical, operational, and regulatory data into a single document. Our approach included:

  • Detailed assessment of all tow and recycling options (wet tow, dry tow, self-propelled), including feasibility studies for Australian and international yards.
  • Early identification of technical and regulatory gaps, with a “traffic light” system to highlight areas needing further work.
  • Engagement with marine consultants and recent project data to provide realistic cost and schedule estimates.
  • Compilation of contingency plans for a wide range of operational risks (weather, manning, ballast, pollution, emergency response).
  • Clear documentation of regulatory requirements and standards, ensuring all parties understood the approval path.

The outcome

The BoD provided the client with a validated, single source of truth for all future planning and execution. Key benefits delivered were:

  • Early risk identification enabled targeted closure of technical and regulatory gaps, reducing the likelihood of costly surprises.
  • The BoD provided a robust foundation for budgeting, scheduling, and scenario analysis, supporting informed decision-making.
  • The approach maximised value by identifying opportunities for local content and minimising environmental and reputational risk.