The client engaged Floating Solutions Consulting (FSC) to review and advise on options for extending the operational life of an FPSO hull. This work was critical to inform decision-making on whether to proceed with decommissioning or invest in a further life extension.
The challenge
Extending the FPSO’s life presented significant technical, operational, and commercial challenges. The main issues identified were:
- The need to complete extensive hull inspections and steelwork renewals, some of which would require production shutdowns or additional infrastructure if done offshore.
- Offshore steel repairs were found to be impractical, with durations exceeding five years and major impacts on production.
- Planning for a dry dock campaign required careful alignment with regulatory inspection cycles, risk-based inspection (RBI) plans, and class requirements.
- High levels of uncertainty in steel renewal quantities, costs, and schedule.
- Managing legacy design anomalies, ongoing coating maintenance, and the risk of new issues being discovered during shipyard surveys.
Our solution
FSC delivered a comprehensive technical review and scenario analysis, providing clear, actionable options. The approach included:
- Detailed breakdown of inspection and steelwork requirements for life extension, including what could be completed offshore versus in dry dock.
- Generation of four steel renewal scenarios, with robust estimates for steel weight, cost, and schedule, and clear identification of the most probable case.
- Identification of inspection efficiency opportunities by deferring difficult or high-impact inspections to the dry dock campaign.
- Guidance on updating the RBI plan, including the need for a full review and re-approval by Class if life extension was pursued.
- Recommendations for early planning, including establishing a shipyard team, developing workpacks, and engaging with regulators and class.
The outcome
The study provided the client with a robust basis for decision-making on the future of the FPSO. Key outcomes and benefits included:
- Clear definition of the technical and commercial requirements for both decommissioning and life extension scenarios.
- Quantified cost, schedule, and risk for each option, enabling informed investment decisions.
- Identification of the impracticality of large-scale offshore steel repairs, confirming the need for a dry dock campaign for any life extension.
- Opportunities to optimise inspection schedules and reduce future operational disruption by aligning inspections with dry dock activities.
- Practical planning guidance to support safe, efficient, and compliant asset management.