Steel renewal estimate improves cost certainty for FPSO drydock

We helped Woodside improve cost and schedule certainty for their upcoming drydock campaign by independently reviewing steel renewal estimates for the Ngujima-Yin FPSO. Our engineering-led assessment identified high-risk tanks, quantified contingency ranges, and provided a methodology to reduce uncertainty and avoid surprises in the yard.

The challenge

Steel renewal work for Cargo Oil Tanks (COT) and Water Ballast Tanks (WBT) was on the critical path for the NY FPSO drydock project. Shipyard estimates were based on limited inspection data, creating high uncertainty in scope and cost. The risk of major overruns due to emergent work was significant.

Key issues included:

  • Limited UT measurement coverage to determine areas at risk of exceeding renewable corrosion criteria before end of life.
  • Discrepancies between inspection findings and shipyard estimates.
  • Lack of verification for previously repaired anomalies.
  • High uncertainty in repair sizing due to incomplete data.

Woodside applied a proactive corrosion renewal philosophy to ensure hull integrity for 10 more years. However, standard inspection coverage was insufficient to accurately define the scope, leading to repair area contingency estimates as high as 2800%.

Our solution

We conducted an independent engineering review of inspection data and Keppel’s steel renewal estimates. Our structured methodology included:

  • High-level review of all tanks.
  • Detailed review of five critical tanks.
  • Development of confidence factors for scope alignment, data quality, and inspection coverage.
  • Quantitative contingency for anomaly repairs (~40%).
  • Qualitative contingency for corrosion renewals.
  • Recommendations for additional inspections and scope refinement.

The outcome

Our study delivered a risk-based steel renewal estimate that highlighted tanks with the highest cost and schedule risk. We enabled Woodside to:

  • Plan for realistic contingencies.
  • Prioritise inspections to reduce uncertainty.
  • Avoid surprises in the yard and protect schedule.