FSC were tasked to assess the structural integrity of an FPSO’s hull, topsides, flare tower, and tow points to confirm suitability for unmanned tow to a recycling facility.
The challenge
The project required a clear understanding of the structural limits for each critical component and how these matched the metocean conditions along the tow route. The main issues were:
- Uncertainty over the limiting sea states for each critical structure (hull, topsides, flare tower, tow points).
- The need to match structural limits to metocean data along the proposed tow route, identifying any weather restrictions or operational delays.
- Ensuring that the tow could be performed safely and without structural failure, even in the most demanding sectors of the route.
Our solution
We reviewed all available structural documentation and original design data, and compared these limits to metocean data for each sector of the tow route. Our approach included:
- Determining the limiting sea states for each structure, using Lloyd’s Register and project-specific criteria.
- Identifying where weather restrictions would apply and quantifying the risk of weather delays.
- Providing clear guidance on both weather-restricted and unrestricted tow scenarios, including potential delays and contingency planning.
The outcome
Our review confirmed that the tow was feasible, provided weather restrictions were observed in the southern sector. The main benefits delivered were:
- Quantified risk of weather delays (e.g. up to 48 hours in the worst month).
- Clear, actionable recommendations for tow planning, risk management, and scheduling.
- Assurance that all critical structures are fit for purpose, supporting safe and compliant asset relocation.